Sun Valley Friedman Memorial Runway Rehabilitation
Hailey, ID
30-day runway rehabilitation completed before Memorial Day weekend
Ardurra delivered critical runway rehabilitation services for Friedman Memorial Airport (SUN) through a 25+ year partnership, successfully completing a complex project within an unprecedented 30-day spring construction window in 2022. The single-runway commercial service airport required precise coordination to minimize community impact while ensuring completion before the Memorial Day weekend, as a runway closure would result in a complete airport closure.
The rehabilitation included mill and inlay of Runway 13-31, paved shoulders, blast pad construction, and complete runway lighting replacement. Strategic planning addressed local construction hour limitations, weather constraints, and material logistics while maximizing on-site recycling to reduce truck traffic on local roads during the critical construction period.
Key Project Management Strategies:
-
Completed runway rehabilitation within 30-day closure, ensuring the airport reopened before Memorial Day weekend through precise scheduling and coordination
-
Analyzed historical weather records, identifying an optimal 30-day construction window, minimizing weather-related delays and complications
-
Coordinated extended working hours with City approval, overcoming local ordinance limitations during the critical construction period
-
Maximized on-site material recycling, reducing truck traffic impacts on local roads while supporting sustainable construction practices
-
Bid project one year in advance, ensuring discretionary grant funding availability before the construction window opening
-
Managed complex logistics coordination across all project elements, including milling, paving, lighting installation, and material management
-
Completed ribbon-cutting ceremony hours before runway reopening and first aircraft landing despite challenging weather conditions
The project demonstrated exceptional coordination capabilities, overcoming cold temperatures and significant precipitation challenges. Strategic advance planning and stakeholder coordination enabled completion within the critical timeline, ensuring that Sun Valley's aviation connectivity remained minimally disrupted while upgrading essential infrastructure to support continued commercial service operations.